HydroInterOp examples for hydro-power plant modeling

I uploaded HydroInterOp examples for libiec61850. These examples are provided by Denis Francesconi (Hydro Quebec) to show how to use data models for hydro power plants based on IEC 61850-7-410. The HydroInterOp examples are a forward step in the development of inter-operable and interchangeable plant level IEDs for hydro power plants (HPP), that is one step closer to having “HPP ready” certified IEDs. HydroInterOp is based on the ongoing work within IEC-TC57 WG18 to develop an implementable hydro information model and conformance test cases based on the IEC 61850 suite. Currently the WG18 is working on a conformance test case document IEC TS 61850-10-210.
The examples work with libIEC61850 version 0.8.4 out of the box. In order to be used with more recent versions of libIEC61850 the data models (static_model.c/.h) have to be recreated by the genmodel.jar tool.

One thought on “HydroInterOp examples for hydro-power plant modeling

  1. Ganesh Shete

    hi sir i am a Engg. student from Instrumentation background & i want to do substation automation by using IEC 61850 as my project n currently i hardly knows anything about it..so can u guide my or give some suggetions???
    waiting for your valuable response..

    thanku..

    Ganesh Shete